Woodbury Renovation

The renovated Woodbury building will house students in Grades 6-8 as they begin the Middle Years Programme (MYP). Updated facilities, including modern classrooms and a newly built auditorium and natatorium, will provide a high-quality learning environment for our students to thrive.

This rendering shows the front view of Woodbury from South Woodland.
This rendering shows an entrance to Woodbury.
This rendering shows the west addition at Woodbury.
This rendering shows an entrance to Woodbury.
This rendering shows part of the new addition to Woodbury.
This rendering shows part of the addition at Woodbury.
This rendering shows the front entrance to Woodbury at night with site lighting.
This rendering shows an entrance to Woodbury at night with site lighting.
This rendering shows part of the new addition at Woodbury at night with lighting.
This slide shows shows the evolution of Woodbury renderings from January to June of 2025.

WALK THROUGH THE WOODBURY INTERIOR

our vision

The renovated Woodbury building will house students in Grades 6-8 as they begin the Middle Years Programme (MYP). The remodeled school will include the center of the original building, which was built in 1918, along with secure entrances and ADA accessibility. The new construction will include modern classrooms, an auditorium and a natatorium. 

MASTER FACILITIES PLAN

The Woodbury renovation project is a part of the District's Long-Term Master Facilities Plan. 

Learn about the plan

Middle Years programme

The Middle Years Programme (MYP) links student experiences across middle school and high school. 

middle years PROGRAMme INFO

DISTRICT SUSTAINABILITY PLAN

The Shaker Heights Schools partnered with Emerald Built Environments, a Cleveland-based sustainability consultant, to develop a District Sustainability Plan. 
 

read sustainability plan

A construction site with a partially built concrete structure in the foreground and an old brick building with a smokestack in the background under a cloudy sky.
Red plastic barriers and rebar mark the foundation of a construction site in the foreground, with a brick building and a concrete wall under construction in the background.
A V-shaped foundation with rebar protrudes from the muddy foreground, while a large brick building with a tall smokestack and a new concrete structure stand in the background under a cloudy sky.
Foundation walls at Woodbury construction site
East view of Woodbury construction site
Woodbury construction site looking east
Woodbury construction site looking northwest
This graphic on the Woodbury construction fence shows a rendering of the new building, along with logos for the schools, architects, construction company, and OFCC.
This picture shows the red mesh on the construction fence at Woodbury.
An excavator tears down the pool at Woodbury as the start of partial demolition at the site. There is a pile of rubble in the foreground.
This image shows a zoomed in view of the construction fence around Woodbury, with rubble in the background behind the fence.
A construction worker stands along the fence around Woodbury for installation.

renovation update

All foundation work at the Woodbury site has been completed. Contractors continue to install waste and vent infrastructure underground for lockers, showers and restroom areas around the natatorium and gym. They are also installing underground electrical in this area, and masonry walls are underway. In the coming days, contractors are working on steel framing in the current 1918 building and ongoing masonry work in the new classroom wing, natatorium and gym.

For the latest updates, sign up for the Facilities Update newsletter.

 

Recent Woodbury Renovation News

Revised Woodbury renderings were presented to the Board of Education at its November 11, 2025 meeting. Board members provided positive feedback on interior and exterior renderings that showed the school entrances, landscaping, lighting and more.

In early November 2025, the City’s Architectural Board of Review (ABR) and Planning Commission approved District plans related to the renovations at the Woodbury school building. The approvals by these two City commissions are significant as they will enable the Woodbury renovation project to continue on schedule.

The partial demolition of Woodbury is nearing completion. The gym, pool, east wing and west wing were demolished from July through October 2025. Gilbane Building Company continues to remove debris from the site before beginning work on the foundation.

On June 10, the Board of Education approved a Guaranteed Maximum Price (GMP) resolution from Gilbane Building Co. for the second phase of construction at Woodbury.