Spring/Summer 2016 Capital Improvement Projects Update

Beginning this month, the Shaker Heights City School District will be engaged in several improvement projects.

  • The tennis courts at Parkland Drive and Ashford Road will be closed from May 9 to August 8 for renovation and resurfacing. 
  • The parking lot at the Administrative Building will be closed for resurfacing from June 13 to July 1. Administrative offices will remain open during this period with parking available on the street and at Onaway Elementary School. 
  • Work will begin June 6 on replacement of the Woodbury School clock tower at 15400 S. Woodland Rd. The work is expected to be completed by August 1. A construction fence will be set up around the perimeter of the front entrance of the school to protect the site during installation of the new clock tower. All school operations will continue during construction. 
For questions, please contact the District Communications Office.